Product migration

Last change on 2026-01-27 • Created on 2023-11-30 • ID: GE-22B1F

This article describes the options for transferring products between different Hetzner accounts. The procedure differs depending on the platform: Robot, Hetzner Console, or konsoleH.

Robot products

Dedicated root servers

For dedicated servers, the following article describes how to do the transfer: Server transfers between Robot customers

Domains

You can transfer domains directly on Robot by the previous contract partner.

Procedure:

  • Person A = current owner
  • Person B = future owner
  1. Person A selects the domain they want to transfer on Robot under Domains.
  2. Person A creates a transfer token by going to Create token and gives the token to Person B. The token is valid for 7 days.
  3. Person B goes to their account on Robot and starts the transfer under Domains → Show domain transfers → Start domain transfer and enters the token.
  4. Person A receives an email and confirms the transfer on Robot by going to the Transfer tab.
  5. The transfer is automatically carried out and Person B receives a notification when it is finished.

Note: An existing AV contract is not automatically transferred and must be renewed if necessary.

Rackspot

  • Person A = current owner
  • Person B = future owner

You can transfer rack space reservations in two ways:

  • Person A fills out a form
  • Both Persons A and B send support requests using their Robot accounts:
    • Person A opens a ticket with transfer request
    • Person B opens another ticket and agrees to the transfer

vSwitch

It is not possible to transfer a vSwitch. If you want to transfer a server that is connected to a vSwitch, you need to first remove the vSwitch. Then transfer the server from Person A to Person B (see steps above). And then assign the server to a vSwitch on Person B's account.


Hetzner Console products

General

The same process applies to most resources. These resources can be transferred via a shared project:

Primary IPs, Floating IPs, cloud servers, Storage Boxes, Volumes, Snapshots, DNS zones.

Procedure:

  • Person A = current owner
  • Person B = future owner
  1. Person B creates a project and invites Person A. (See below.)
  2. Person A moves the resource to this project.
  3. Person B moves the resource to a private project.

Load Balancers

It is not possible to transfer Load Balancers between projects. However, you can move the IP address of the Load Balancer to the target project and create a new Load Balancer with that same IP address.

  1. Delete the old Load Balancer in the source project and select "Keep as unassigned" for the IP address.
  2. Move the Primary IP, which is now unassigned, to the target project.
  3. Create a new Load Balancer in the target project and select the Primary IP of the old Load Balancer.

Private Networks/Firewalls

It is not possible to transfer Networks and Firewalls between projects.
You have to recreate them in the target project:

  1. Create a new Firewall or Network in the target project.
  2. Add rules or resources.

Object Storage

It is not possible to transfer Object Storage Buckets between projects. To move them, you need to replicate the data:

  1. Create a new bucket in the target project.
  2. Transfer the data using tools such as rclone.

Project invitations on Hetzner Console

To add a member to a project:

  1. Open the project.
  2. Select Security in the left-hand menu.
  3. Open the Members tab.
  4. Add member

For more information, see: What are projects and how can I use them?


konsoleH Products

Web hosting packages, Storage Shares & Managed servers

Unfortunately, we are generally unable to carry out manual transfers.
Storage shares, web hosting packages and managed servers cannot be transferred.

Managed Domains

As a gesture of goodwill, we can manually transfer domain registrations only. Please note, however, that you will always have to transfer the data yourself.

Table of Contents